Unit Complex Repair

A Unit complex at Algester.
NBN had laid their new services to all residents in the complex.
450 meters of the trench had to be backfilled and surfaced with new Asph

.

Bitumen and Asphalt Repairs 2
Bitumen and Asphalt Repairs 3

Uneven Surfaces

Jeep wreckers in Hervey Bay.
This area was unlevel to the stage the forklift had difficulty driving over.  Removal and increasing the base thickness and then replacing the Asphalt. All completed within half a day.

Joining to new Kerbing

Crestmead
Kerb and channel with drainage had been installed after the road had been constructed.
We saw cut the existing road to a uniform width then laid Asphalt to 40mm.   
Bitumen and Asphalt Repairs 4
Bitumen and Asphalt Repairs 5
Bitumen and Asphalt Repairs 6

Road Repair

Housing development west of Maryborough.
The road had failed in various areas due to the developers not addressing the ground conditions thoroughly and not building the road to suit.
The road needed to be repaired before the council would allow any property sales to go ahead.
We removed all the damaged areas and laid cement-treated roadbase to 250mm then surfaced with Asphalt.

Driveway Repair

Previous contractors installed mismatched pipes and eventually started to fail with the above driveway starting to disappear where the pipe ends meet.

Complete removal and replacement of a new headwall and larger pipes than original.
Then the correct procedure with backfilling around pipes and finally resurfacing with Bitumen.
Bitumen and Asphalt Repairs 7